Selected equipment supply references

Home/Products/Selected equipment supply references

Selected equipment supply references

Examples of equipment supplied by SBCCO-China and references from our sister company. Quantities, vessel capacities and shipment dimensions describe the individual projects. Sister-company examples are identified beside the case. The references help you find comparable work when preparing a new enquiry.

02

Equipment and recorded quantities

FRP launders for 73.2 m thickeners

Industry
Mineral processing
Customer / project
WesTech reference, Puerto Rico
Problem
Collect and route thickener overflow.
Solution
FRP launder systems for the host thickeners.
Recorded result
The WesTech supply reference records two FRP launder systems in 73.2 m diameter thickeners in Puerto Rico. The diameter describes the host thickeners, not the diameter of a shop-built FRP tank. The supply scope was the launder systems; the record does not establish a complete thickener design or a process-throughput guarantee.

Reference supplied by our sister company, Crimar Industrial.

28 m³ acid wash column for FLSmidth

Industry
Mineral processing
Customer / project
Crimar / FLSmidth, June 2016
Problem
Provide a vessel for acid washing.
Solution
FRP acid wash column to the recorded design basis.
Recorded result
The FRP reference list records one 28 m³ acid wash column for Crimar / FLSmidth in June 2016, with ASME RTP-1 as the recorded design code. This is a project reference for a particular vessel and service. A new column requires its own chemical duty, dimensions, laminate design and inspection requirements; the historical code entry is not a claim that every fabricator holds an ASME authorization.

Reference supplied by our sister company, Crimar Industrial.

PASAR acid-service pump tank

Industry
Copper smelting
Customer / project
PASAR
Problem
Provide a pump tank for acid service.
Solution
FRP pump tank with documented shipment packing.
Recorded result
The 2019 FRP reference list records one 47 m³ pump tank for PASAR. SBC’s packing list dated 12 June 2019 records the pump-tank shipment at 4,090 kg net and 6,500 kg gross, with a 5,100 × 5,100 × 4,300 mm shipping envelope. Those dimensions describe the packed shipment. They are not the tank’s internal dimensions, and the gross weight is not the vessel design weight.

15,600 kg mill cover shipped to Chile

Industry
Mineral processing
Customer / project
Wiedco supply reference, Chile
Problem
Replace a mill component.
Solution
Mill cover packed and shipped as a documented replacement.
Recorded result
SBC’s packing list dated 15 January 2019 records one mill cover shipped to Chile through Wiedco. The listed net weight is 15,600 kg, gross weight 17,100 kg and package size 3.5 × 3.5 × 1.55 m. This is an actual shipment reference for a replacement mill component. Package size does not establish the casting’s finished diameter, and the record is not a maximum foundry or machining capacity.

1,580 kg trunnion liner for a Chilean ball mill

Industry
Mineral processing
Customer / project
Molino Bola 18A, Chile
Problem
Replace the trunnion liner.
Solution
Pack and ship the replacement part.
Recorded result
The 2025 shipment packing list for the Molino Bola 18A replacement records one trunnion liner, 1,580 kg net, in a 1,700 kg gross package. The shipping package measures 172 × 172 × 155 cm. The reference demonstrates a documented replacement-part shipment; it does not state an operating-life result or confirm interchangeability with a different mill.

1,893 kg mill girth gear for Chuquicamata

Industry
Copper mining
Customer / project
Codelco Chuquicamata, via Wiedco
Problem
Replace a mill drive component.
Solution
Marcy girth gear with documented packing.
Recorded result
SBC’s packing record for a Marcy mill girth gear identifies the destination as Codelco Chuquicamata through Wiedco. It records one gear at 1,893 kg net and 1,910 kg gross, packed at 2,900 × 1,470 × 700 mm. These are shipment figures. Gear accuracy, tooth geometry, material and heat treatment for any replacement must be established from that replacement’s approved drawings and acceptance requirements.

Two inspected stainless steel tube bundles for Minara

Industry
Metallurgical processing
Customer / project
Glencore / Minara
Problem
Provide bundles for a hot-acid exchanger.
Solution
Stainless steel bundles with third-party inspection.
Recorded result
The Glencore project reference identifies two stainless steel tube bundles for Minara’s hot-acid heat exchanger in 2019. The third-party inspection report dated 9 January 2019 covers two tube bundles, with material-record review, dimensional checks, tube-to-tubesheet inspection and witnessed hydrostatic testing among the stated activities. The example concerns replacement bundles and their inspection scope, not the thermal design of an entire acid plant.

PASAR order for 20 lined valves

Industry
Copper smelting
Customer / project
PASAR
Problem
Specify valves for corrosive service.
Solution
Select lined valves by type and line size.
Recorded result
PASAR’s August 2019 purchase order to SBC specifies 20 lined valves across ten order lines: 16 PFA-lined gate valves, two PFA-lined globe valves and two PTFE-lined butterfly valves. Nominal sizes in that order run from 50 to 250 mm. This is the recorded order scope, supported by the PASAR supply reference; it is not a pressure-temperature rating or a new delivery promise.

Lined dampers for a copper smelter in Indonesia

Industry
Copper smelting
Customer / project
Freeport-McMoRan, Indonesia
Problem
Control corrosive gas flows.
Solution
Specify lined dampers by duty. PFA was limited to the surge-line item.
Recorded result
The packing list documents 11 dampers at 5,511 kg net and 6,290 kg gross. The QC file records the inspections and tests.

Reference supplied by our sister company, Crimar Industrial.

FLSmidth lamella packs for potash thickeners

Industry
Potash processing
Customer / project
FLSmidth, Canada
Problem
Provide internals for thickener equipment.
Solution
Configure inner and outer lamella sections to the two thickener arrangements.
Recorded result
The orders identify 18 m and 26 m host thickeners. The purchase orders, packing list and manufacturing reports document the supply scope.

Reference supplied by our sister company, Crimar Industrial.

FLSmidth gold plant acid wash assembly in Guyana

Industry
Gold recovery
Customer / project
FLSmidth, Guyana
Problem
Provide an acid wash assembly for an ADR plant.
Solution
The scope lists an FRP screen, nozzles and flanges, with alloy laterals furnished by FLSmidth.
Recorded result
The scope sheet records a 10 t assembly. Fabrication and assembly reports, the packing list and manufacturing records document the work.

Reference supplied by our sister company, Crimar Industrial.

Project reference questions

What do the project figures describe?

They describe the recorded order, shipment or inspection for the case shown. Shipping sizes are the packed dimensions where stated.

Who supplied the sister-company projects?

The small note on each relevant case credits Crimar Industrial for that reference.

What is needed to quote a similar item?

Provide the drawings, service conditions, quantities and inspection requirements for your order.

03

Use a comparable project to define the new duty

Send the project location, equipment description, operating conditions, drawings and required delivery date. We can identify a relevant supply example and define the scope for your new equipment. A successful shipment records what was supplied; a new operating duty still needs its own materials, design, interfaces and inspection requirements.